Frequently Asked Questions
- I-49 Lafayette Connector
- 5
- The Project
- 5
- Frequently Asked Questions
The Project
Frequently Asked Questions
Planning Background
Defatult Closed
How was the current corridor chosen? What were the reasons behind it?
In 1993, the Lafayette Areawide Planning Commission initiated a six-month study of the possible corridors for the I-49 Connector. Their findings were published as the Lafayette North-South Corridor Study: Path to Progress, which can be found on the project website here: https://lafayetteconnector.com/download/lafayette-north-south-corridor-study-path-to-progress/.
The Path to Progress evaluated four possible corridors and structure types. The criteria used to judge each option included traditional highway cost/benefit, public safety, environmental effects, and quality of life. The Evangeline Thruway was determined to be the best corridor.
In 2001, following a Public Hearing on the Draft Environmental Impact Statement (EIS), the Lafayette City-Parish Council, in its capacity as the Lafayette MPO, adopted a resolution to approve and identify the Locally Preferred Alternative Alignment as Alternative RR-4 with Sub-alternative F (MPO Sub-alternative) and Sub-alternative H. This is the alternative that was approved in the 2003 Record of Decision (ROD), which can be found on the project website here: https://lafayetteconnector.com/download/record-of-decision/.
The current work is a Supplemental EIS (SEIS) to determine the environmental effects of modified alternatives, also within the Evangeline Thruway corridor, and to identify the measures required to avoid, minimize, or mitigate any adverse effects.
How can the public give input?
Since the project was reinitiated in 2015, an extensive community outreach process has been conducted, which, to date, has substantially modified the alternative defined in the 2003 ROD. As the design is further examined by DOTD, and by the community through the Context Sensitive Solutions (CSS) process that includes neighborhood, public and committee workshops, other modifications are being considered. At the end of this evaluation phase, a Preferred Alternative will be identified in the Draft SEIS.
Following a Public Hearing, a Record of Decision (ROD) identifying the selected alternative will be issued by FHWA. The project will advance into the Final Design and begin construction after the issuance of the ROD based on funding availability.
What is a Supplemental EIS (SEIS) and why is it being prepared?
An SEIS is prepared when new alternatives and/or new information needs consideration following a ROD. An SEIS is being prepared for this project because new alternatives were identified in 2017 and must be evaluated and compared to the 2003 ROD Alternative.
What is the purpose and need of the I-49 Lafayette Connector project?
The purpose is to complete I-49 South to connect Lafayette and New Orleans; the needs of the I-49 Connector include:
- System Linkage
- Existing and Projected Traffic Conditions
- Regional Transportation and Land Use Plans
- Legislation and Governmental Support
- Modal Interrelationships
- Safety
- Hurricane Evacuation
- Economic Factors
Project Funding
Default Closed
How will the I-49 Connector project be funded?
Typically, the capital and maintenance costs of the roadway transportation improvements and any mitigation of adverse impacts are funded by the DOTD with assistance from the FHWA. Other project elements, for example street lighting, might be constructed by DOTD but would be maintained by the local authority responsible for street lighting. The construction, as well as the maintenance of any non-transportation-related joint use projects, would typically be financed by others. Funding resources and delivery methods for the project as well as the phasing of the construction will, in part, be determined by available funding.
Are improvements to the Evangeline Thruway included as part of the cost of the overall I-49 Connector project? Will local funding be required and what input will local government have in the design and alignment choices?
Cost related to reconstruction of Evangeline Thruway as a one-way couplet or as a boulevard will be included in the cost of the overall project. It is unlikely that the city would have construction cost responsibilities unless it requests modifications or additions to the design beyond what the state typically would construct. However, local governments typically are responsible for maintenance of sidewalks, lighting, landscaping, and other street amenities.
What parts of a project have a “transportation purpose”? Who would make that determination? Are the mitigation measures required by the Record of Decision considered “transportation purposes"?
The “transportation purpose” of a project is the project element or elements that meet the Purpose and Need. In the case of the I-49 Connector, this is the construction of an interstate highway connecting the I-49/I-10 interchange with the next I-49 segment in the vicinity of the Lafayette Regional Airport. Other transportation elements, such as improvements to the Evangeline Thruway and certain bicycle and pedestrian facilities related to the interstate highway, may be found to have a transportation purpose and may be eligible for transportation funding. The FHWA would make the decision. Also eligible for transportation funding are the measures identified in a ROD as mitigation for the adverse impacts of the elements with a transportation purpose.
Have costs for the remediation of toxic sites and protection of the drinking water been identified?
A Phase I Environmental Site Assessment (ESA) has been completed for the corridor. Currently, Phase II ESAs are being conducted in those areas of the proposed right-of-way as indicated by the Phase I findings and as required by the Louisiana Department of Environmental Quality (LDEQ).
Any remediation costs will be estimated pending completion of the Phase II ESAs, the determination of remediation measures, and the identification of a preferred alternative.
Design Issues
Default closed
How will people access downtown?
Entrance and exit ramps, both north and south of Downtown, are planned to replace the interchanges at Johnston Street and 2nd/3rd Streets that were included in the 2003 ROD Alternative. These ramps would connect with a rehabilitated Evangeline Thruway that would intersect with local streets leading into Downtown.
How will the water runoff from the elevated highway be controlled?
The runoff from an elevated highway, if there is sufficient capacity in the storm water system of the surrounding area, can be directed into that system. If the capacity is not available, other measures, such as additional/larger storm sewer systems and/or retention or detention ponds, could be employed. The necessary analysis to determine how the runoff from the Connector will be directed has not been completed.
Will the I-49 Connector require the relocation of a runway at the Lafayette Regional Airport?
The 2003 ROD alternative would have resulted in the relocation of a runway, but it is anticipated that the Federal Aviation Administration will approve a modification that is intended to eliminate the relocation.
How high will the elevated highway be above the ground?
One of the commitments in the 2003 ROD states “DOTD will provide the provision of increasing the elevation of the roadway structure above the minimum requirement.” This has resulted in the current plan to elevate the roadway structure to 22 feet above the ground, which exceeds the minimum requirement of 16 1/2 feet. Depending on further community input, other heights could be considered.
Will there be a separation between the northbound and southbound lanes?
The current plan is that the structures would be 10 feet apart in Downtown and 5 feet apart elsewhere. Again, depending on further community input, other distances could be considered.
How does the Connector, which is intended to move traffic over long distances, work for the locals who would use it for local trips?
The corridor is being planned to provide six lanes for mid- and long-distance trips on the interstate and four lanes for local trips on the Evangeline Thruway. This will give regional and local travelers the option of using either the Thruway or the interstate depending on where they would get on and where they are going. This plan greatly removes longer distance through trips from the surface streets, which will reduce congestion on the Thruway and the local network.
When will the bicycle and pedestrian infrastructure be discussed?
There has been some discussion of bicycle and pedestrian infrastructure, but it is best to study detailed plans for these improvements after the alignments of the alternatives are determined. Also, state and local Complete Streets policies must be considered.
What are Complete Streets policies?
Complete Streets is a transportation policy and design approach that plans, designs, operates, and maintains streets to provide access, mobility and safety, for users of all ages and abilities regardless of their mode of transportation.
Is there a federal or state requirement that streets that function as part of a frontage road system be one-way or have limited access?
No, but there are Control of Access restrictions on frontage roads and connecting roads relative to ramp terminals.
Will a design speed that is more neighborhood-friendly than the existing posted speed be considered for the Evangeline Thruway?
With much less traffic expected on the Thruway, a lower design speed along the Evangeline Thruway will be considered during the traffic evaluation.
Have any traffic analyses been run to determine the capacity that the local grid network could handle during evacuation events?
No, because the I-49 Connector is intended to provide the capacity needed during evacuation events. However, the Acadiana Planning Commission has evaluated the impacts of the I-49 Connector on the local grid system and found a positive impact on the local grid.
What is the difference between a “Signature Bridge” and a “landmark feature”?
A “Signature Bridge” is an iconic, typically long-span structure, that can be architecturally significant and have potential historic and cultural references. A “Landmark Feature” could take many forms, including a Signature Bridge, to enhance the overall transportation corridor for identity and place-making purposes, but could include gateway monuments, large-scale landscape elements, major public art features and other urban design features.
What will be the access to the neighborhood between the Union Pacific RR Spur and Chopin Street?
This will be discussed with the Lafayette Consolidated Government (LCG), the residents of this area, and Sterling Grove Historic District and will take place during the neighborhood meetings that are planned as part of the CSS process and through other community outreach efforts.
Is an effort being made to address potential economic development?
An analysis of the potential for the alternatives to stimulate economic development is not part of the current I-49 Connector project. However, a number of design elements that could stimulate or complement economic development are included and will be discussed during the CSS process with the LCG and other stakeholders.
When will the alignment alternative be set?
The alignment was selected in the 2003 ROD and follows the existing Evangeline Thruway corridor. DOTD currently is evaluating the modifications that came out of the Concept Refinement Phase in 2017. The SEIS will evaluate the modifications and the final decision with regard to the refinements will be published in a Record of Decision following the public hearing on the Draft SEIS.
Historic Preservation
Default closed
How will the historic neighborhoods be protected?
Section 106 of the National Historic Preservation Act (NHPA) requires that the Advisory Council of Historic Preservation (ACHP) be given an opportunity to comment on the potential effects of a project on historic resources. When a project begins, the sponsoring agencies, in this case FHWA and DOTD, contact the State Historic Preservation Officer (SHPO) to initiate the Section 106 process. In most cases, following a consultation process, this results in a Memorandum of Agreement (MOA) between the sponsors, the FHWA, and the SHPO that defines the measures to mitigate any adverse effects. If these parties cannot agree, the ACHP considers the unresolved issues.
A MOA was signed in 2002; why would there be a new one?
A new MOA will be needed for three principal reasons:
- The 2002 MOA expired in 2017;
- The project has changed in many ways; it will have different effects on historic resources and, potentially, require different mitigation measures; and
- There is a new historic district, Freetown-Port Rico, that has been listed on the National Register of Historic Places (NRHP).
Is the Section 106 process underway? What are its findings?
The Section 106 process has three principal steps: identification of the resources, determination of the effects, and development of mitigation measures. The first of these is complete. See the Historic Architecture Resource Inventory Update, Volumes I and II at the following link: https://lafayetteconnector.com/project-library/#section-106
The other steps cannot be undertaken until the modified alternatives have been defined which is currently underway as part of the DSEIS process.
Will the project impact any historic properties?
The project currently is not anticipated to have a direct physical impact on any historic properties. However, while the 2003 ROD alternative had multiple adverse effects, the current Analysis Alternatives (C-5 and C-6) have been determined to avoid adverse visual impacts to the Sterling Grove Historic District, though they may still have effects on the Freetown-Port Rico Historic District.
Potential Impacts and Mitigation
Default closed
How will the aquifer be protected?
Two of the commitments in the 2003 ROD address this issue:
Commitment 3.9 acknowledges the potential for contamination through groundwater/surface water interchange and states that this will be addressed through special design techniques and plan review procedures involving USEPA, LDEQ, and other appropriate agencies.
Commitment 3.7 offers the following special design techniques that could be used:
- Excavation to a depth of 15 ft, disposal at an appropriate offsite location, and backfilling with clean material;
- Excavation to a depth of 5 ft, disposal at an appropriate offsite location, capping the excavated area, and backfilling with clean material;
- Excavation of footing locations only; and
- Drilling (instead of pile driving) and using a slurry seal to prevent downward migration of contamination.
No decision has been made pending completion of the Phase II Environmental Site Assessment.
How can highways assist with revitalization?
One way a highway can assist future development is by reducing congestion and improving connectivity. This project is designed to accomplish both.
Has a Noise Analysis been completed?
No, noise analysis typically is done after the alternatives have been defined.
What joint uses would be possible where the highway will cross property that may be contaminated?
The area that may be contaminated between Taft/16th Street and 3rd Street currently is designated as suitable for Industrial use by the Louisiana Department of Environmental Quality (LDEQ).
Section 2.9. Land Use of LDEQ’s Risk Evaluation / Corrective Action Program (RECAP) states “Current and future land use shall be determined in order to characterize the activities and activity patterns of the potentially exposed population. The current and future land use category … is subject to Department approval.”
Section 2.9.1 Industrial/Commercial states “Industrial/Commercial land use refers to any property not currently used for human habitation on a permanent or temporary / intermittent basis…” It goes on to list hundreds of specifically allowed uses, using the North American Industry Classification System (NAICS).
Allowed uses include many types of businesses, hotels, fitness clubs, and much more. Disallowed uses include childcare and child social service facilities; kindergarten through post-graduate academic institutions; hospitals and residential care facilities; private homes; boarding houses, RV parks; correctional facilities; nature parks; and water supply and irrigation facilities. The NAICS codes are largely meant to help organize data for commercial entities, not all land uses. The code does not include small parks, farmers’ markets, tennis courts, or dog parks. Those uses are not explicitly allowed or disallowed.
More information available on LDEQ website: https://www.deq.louisiana.gov/page/recap